Planned building shutdown: plan it and notify
How to plan a building shutdown for power, water, lift or fire system work, and who to tell, when and how. A guide for facilities managers.
By James Rohloff - - 8 min read
A planned building shutdown is a scheduled period when a building service, such as power, water, lifts, air conditioning or the fire alarm, is turned off so work can be done safely. To run one well, a facilities manager needs a written plan with a start and finish time, a list of everyone affected, notices sent early enough for tenants to prepare, and a record of who received them.
Most shutdowns that go wrong do not fail on the technical work. They fail because a tenant with a critical need was not told, the notice went to an old contact, or nobody confirmed that services were back on. This guide covers how to plan the shutdown, who to tell, when to tell them, and what to check afterwards.
What is a planned building shutdown?
A planned building shutdown is any deliberate interruption to a shared building service that the building owner or manager arranges in advance. It is different from an unplanned outage or an emergency, because you control the timing and you have time to warn people.
Common reasons include:
- Switchboard, transformer or electrical maintenance that needs the power isolated
- Water main repairs, backflow testing or hot water system work
- Lift servicing, modernisation or repairs
- Fire alarm, sprinkler or other life safety system work
- Air conditioning and mechanical plant replacement
- Network, security or access control upgrades
Who needs to know about a building shutdown?
More people than the tenant list. A shutdown touches anyone who relies on the service, anyone working on it and anyone who monitors the building. Build the list before you write the notice.
| Who | Why they need to know | What they need from you |
|---|---|---|
| Tenants | Their staff, customers and equipment are affected | Dates, times, services affected, what to do before and after, and who to call |
| Tenants with critical needs | Server rooms, refrigeration, medical equipment or people who cannot use stairs | An early, direct conversation, not just the general notice |
| Contractors doing the work | They need access, isolations and the agreed timetable | Access details, the site induction, permits and the on-site contact |
| Other contractors booked that day | Their work may not be possible without power, water or lifts | A heads-up so they can reschedule |
| Security and after-hours providers | Alarms, access control and cameras may behave differently | Times, expected alarms and who is on site |
| Alarm monitoring company | Fire or security alarms may be isolated or triggered during the work | Isolation times and the contact who will restore them |
| Owner or asset manager | They carry the risk and may need to approve the work | The plan, the cost and any tenant impact |
If your tenant list is out of date, fix that first. Our tenant contact list template and contractor contact list guides cover what to keep and how to keep it current.
How much notice should tenants get?
Check the lease first. Many commercial leases say how much notice the landlord must give before entering a tenancy or interrupting services, and that sets your minimum. Beyond the lease, give as much notice as the work allows. A practical rhythm for a planned shutdown is:
- First notice, as soon as the date is confirmed. Give the date, time, services affected and a contact. This lets tenants plan staffing, trading hours and equipment.
- Reminder, a few days before. Repeat the essentials and add anything that has changed, such as a revised finish time.
- Day-before or morning-of message. Keep it short and send it by SMS, so it is seen.
- All clear, when services are back. Say what is back on, what tenants should check, and who to call if something is not working.
Tenants with critical needs should hear from you before the first general notice, so you can agree how they will manage. That might mean a generator, a later start, or moving the work to a different day.
How do you plan a building shutdown in seven steps?
- Define the scope. Write down which services will be off, which parts of the building are affected, the start time, the expected finish time and a worst-case finish time.
- Check the systems involved. If the work touches fire alarms, sprinklers, lifts or other systems on the building's compliance schedule, involve the contractors and inspectors who maintain them. Make sure the fire safety and evacuation arrangements still work during the shutdown, or that you have an alternative in place.
- Talk to tenants with critical needs. Identify them from your records and call them before you announce the date.
- Book the contractors and confirm access. Share the induction, permits, isolation points and the on-site contact. Confirm the contractor's after-hours number.
- Send the first notice. Use a clear subject line and the same structure every time. Our tenant communication templates include a planned outage template you can adapt.
- Run the day. Have one person in charge, a list of who is on site, and a way to message every tenant if the timing changes.
- Restore and confirm. Check every service is back, any isolated alarms are restored, and lifts are back in service. Then send the all clear.
What should a building shutdown notice include?
A good shutdown notice answers the tenant's questions in the first few lines. Keep the same order every time, so tenants learn where to look.
- What: the services affected, such as power, water or lifts
- When: the date, start time and expected finish time
- Where: the building, floors or areas affected
- Why: a short reason, such as switchboard maintenance
- What to do: turn off sensitive equipment, plan staffing, use the stairs, store food safely
- Who to call: a named contact and phone number, including on the day
Keep the SMS version to the what, when and who to call, with a link to the full notice. Email carries the detail. Our guide to after-hours contact for tenants covers what number to publish when the work runs outside business hours.
What about fire and life safety systems?
Shutdowns that affect fire alarms, sprinklers or emergency lighting need extra care, because they change how a building is protected while people are inside. In New Zealand, building owners must keep the specified systems on a building's compliance schedule inspected and maintained, and renew the building warrant of fitness each year. See specified systems and compliance schedules on building.govt.nz.
Owners also need an evacuation procedure that works, and some buildings need an approved evacuation scheme. Fire and Emergency New Zealand explains these duties on its owner responsibilities page. Talk to your fire protection contractor and alarm monitoring company before isolating any part of a fire system, and get advice for your own building where you need it.
Why do building shutdown notices go wrong?
The same few problems come up again and again:
- The notice goes to a tenant contact who left months ago
- Only the primary contact hears, and the staff who open the shop at 7am do not
- The email goes out but nobody checks whether it was delivered
- The finish time changes on the day and there is no fast way to tell everyone
- Nobody sends an all clear, so tenants call to ask whether it is safe to restart equipment
- Contractors booked for other work arrive to a building with no power
Most of these come down to two things: contact details that are out of date, and no record of who received the notice. If you want to see how much time your team spends chasing contact details, try the contact admin cost calculator.
How can Properlex help with a planned shutdown?
Properlex, the relationship platform for property, lets you write a shutdown notice once and send it by SMS, email and InMail to the tenants, vendors and partners at the properties you choose. You can narrow the audience by contact type, position or tenant type, so the notice reaches the people who open the building, not just the person who signed the lease. See communications.
Every recipient has a delivery status on each channel, so you can see who has the notice and follow up with anyone it did not reach. The same record shows who sent what and when. See delivery reports. Tenants and contractors keep their own team's details current in their free portal, and Properlex asks them to confirm their details on a schedule you set. More on how this works for facilities managers.
Planned building shutdown checklist
- Scope written down: services, areas, start, expected finish and worst-case finish
- Lease notice periods checked
- Tenants with critical needs called before the general notice
- Fire, lift and other compliance schedule systems considered, with the right contractors involved
- Alarm monitoring and security told about isolation times
- Contractors booked, inducted and given access details and an on-site contact
- First notice sent as soon as the date is confirmed
- Reminder sent a few days before, and a short SMS the day before
- Delivery checked, and anyone not reached followed up another way
- Services restored, alarms reinstated and lifts back in service
- All clear sent, with who to call if something is not working
Frequently asked questions
What is a planned building shutdown?
A planned building shutdown is a scheduled interruption to a shared building service, such as power, water, lifts or the fire alarm, so that maintenance or repair work can be done safely. Because it is planned, the building manager can warn tenants and contractors in advance.
How much notice should tenants get for a planned power or water outage?
Start with the notice period in the lease, which is the minimum. Then give as much notice as the work allows, followed by a reminder a few days before, a short message the day before and an all clear when services are back.
What should a building shutdown notice include?
The services affected, the date, start and expected finish time, the areas affected, a short reason, what tenants should do to prepare, and a named contact with a phone number for the day.
Should I send shutdown notices by SMS or email?
Both. Email carries the full detail and SMS makes sure the key facts are seen, especially for the day-before reminder and any change on the day.
What if the shutdown runs late?
Tell everyone affected as soon as you know, with a new expected finish time. One person should own these updates, and you need a fast way to reach every tenant, such as an SMS broadcast.
Do tenants need an app to receive Properlex notices?
No. Notices arrive by SMS and email, and tenants can also read and reply in their Properlex portal in a web browser. Accounts created from your invitation are free for tenants.